During the Acceptance Phase, who tracks RFIs, COs, and SIs?

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

During the Acceptance Phase, who tracks RFIs, COs, and SIs?

Explanation:
During acceptance, the day-to-day coordination of questions and changes is handled by the Cx Technician. The CxT maintains the logs for RFIs, COs, and SIs, routes items to the appropriate parties, tracks responses, and ensures each item is closed before handover. The CxA provides oversight and signs off when the documentation demonstrates the system meets the contract and project requirements, but the primary responsibility for keeping these records and following up on them rests with the CxT. Vendors contribute information and implement changes, but the tracking function itself is owned by the CxT.

During acceptance, the day-to-day coordination of questions and changes is handled by the Cx Technician. The CxT maintains the logs for RFIs, COs, and SIs, routes items to the appropriate parties, tracks responses, and ensures each item is closed before handover. The CxA provides oversight and signs off when the documentation demonstrates the system meets the contract and project requirements, but the primary responsibility for keeping these records and following up on them rests with the CxT. Vendors contribute information and implement changes, but the tracking function itself is owned by the CxT.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy