During the Design Phase, the OPR is translated into _____?

Explanation:
The Owner’s Project Requirements (OPR) are the owner's stated needs and expectations. In the Design Phase, those needs are translated into the Construction documents—the official set of drawings, specifications, and contract information that tell the design team and the contractor exactly what to build and how to meet those requirements. Construction documents communicate the design intent in a way that can be bid, permitted, and constructed, ensuring the project is delivered to satisfy the owner’s goals. While design criteria or final design considerations may be refined during design, the formal deliverable that guides construction is the Construction documents.

The Owner’s Project Requirements (OPR) are the owner's stated needs and expectations. In the Design Phase, those needs are translated into the Construction documents—the official set of drawings, specifications, and contract information that tell the design team and the contractor exactly what to build and how to meet those requirements. Construction documents communicate the design intent in a way that can be bid, permitted, and constructed, ensuring the project is delivered to satisfy the owner’s goals. While design criteria or final design considerations may be refined during design, the formal deliverable that guides construction is the Construction documents.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy