In a Design Build project, the commissioning organizational structure is identified as which entity?

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

In a Design Build project, the commissioning organizational structure is identified as which entity?

Explanation:
In design-build, the owner controls the commissioning process. The owner defines performance requirements, acceptance criteria, and test plans, and then appoints the commissioning authority (CxA) to manage and verify that the systems meet those requirements. The CxA may be internal to the design-builder or a separate consultant, but the commissioning structure—the governance and oversight of commissioning—comes from the owner. The architect focuses on design, the contractor on construction, while the CxA executes the commissioning activities under the owner’s direction.

In design-build, the owner controls the commissioning process. The owner defines performance requirements, acceptance criteria, and test plans, and then appoints the commissioning authority (CxA) to manage and verify that the systems meet those requirements. The CxA may be internal to the design-builder or a separate consultant, but the commissioning structure—the governance and oversight of commissioning—comes from the owner. The architect focuses on design, the contractor on construction, while the CxA executes the commissioning activities under the owner’s direction.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy