In which phase are submittals reviewed and verified?

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

In which phase are submittals reviewed and verified?

Explanation:
Submittals are the documents, shop drawings, product data, and samples the contractor provides to the design team to verify that what will be built matches the design intent. The review and verification of these submittals happen during the Construction Phase, when fabrication and on-site installation are planned and underway. This timing lets the design team confirm dimensions, performance, interfaces with other systems, and code compliance before materials are procured or installed, catching issues early and reducing costly changes later. In the Design Phase, the design is created and submittal requirements are established, but the formal review is carried out during Construction; the Occupancy and Operations Phase is after completion and is not where submittal verification typically occurs.

Submittals are the documents, shop drawings, product data, and samples the contractor provides to the design team to verify that what will be built matches the design intent. The review and verification of these submittals happen during the Construction Phase, when fabrication and on-site installation are planned and underway. This timing lets the design team confirm dimensions, performance, interfaces with other systems, and code compliance before materials are procured or installed, catching issues early and reducing costly changes later. In the Design Phase, the design is created and submittal requirements are established, but the formal review is carried out during Construction; the Occupancy and Operations Phase is after completion and is not where submittal verification typically occurs.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy