The PROJECT HANDOVER MANUAL contains the scope of work for each contractor and details for handover and acceptance.

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

The PROJECT HANDOVER MANUAL contains the scope of work for each contractor and details for handover and acceptance.

Explanation:
The key idea is what a Project Handover Manual is used for. This manual is the owner’s package for turning over the project and taking over operations. It typically gathers operation and maintenance manuals, as-built drawings, equipment lists, warranties, spare parts, training records, commissioning records, and the agreed acceptance criteria and test results that prove the system works as intended. The scope of work for each contractor, however, belongs in the contract and project specifications, not in the handover manual. The manual may refer to these scopes or reference where to find them, but it does not serve as the document that defines what each contractor was responsible for. That separation helps keep the handover focused on how the owner will operate, maintain, and accept the installed systems, rather than restating the original contractual scope. So, the statement is not correct because while handover and acceptance details belong in the manual, the contractor scope of work is defined elsewhere, not contained in the handover package.

The key idea is what a Project Handover Manual is used for. This manual is the owner’s package for turning over the project and taking over operations. It typically gathers operation and maintenance manuals, as-built drawings, equipment lists, warranties, spare parts, training records, commissioning records, and the agreed acceptance criteria and test results that prove the system works as intended.

The scope of work for each contractor, however, belongs in the contract and project specifications, not in the handover manual. The manual may refer to these scopes or reference where to find them, but it does not serve as the document that defines what each contractor was responsible for. That separation helps keep the handover focused on how the owner will operate, maintain, and accept the installed systems, rather than restating the original contractual scope.

So, the statement is not correct because while handover and acceptance details belong in the manual, the contractor scope of work is defined elsewhere, not contained in the handover package.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy