Who is responsible for Acceptance Phase Direct FPTs?

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

Who is responsible for Acceptance Phase Direct FPTs?

Explanation:
Direct FPTs in the Acceptance Phase are led by the Commissioning Authority. The CxA is responsible for planning, executing, and documenting the functional performance tests to confirm that systems meet their design intent and performance criteria. The tests are typically run by the CxA (often with support from a Cx Technician to operate equipment and record data), while the project manager and other team members coordinate schedule and resources and the owner or operator may witness. Shared responsibility isn’t the standard approach for these direct tests, since the tests require the authoritative execution and sign-off by the CxA.

Direct FPTs in the Acceptance Phase are led by the Commissioning Authority. The CxA is responsible for planning, executing, and documenting the functional performance tests to confirm that systems meet their design intent and performance criteria. The tests are typically run by the CxA (often with support from a Cx Technician to operate equipment and record data), while the project manager and other team members coordinate schedule and resources and the owner or operator may witness. Shared responsibility isn’t the standard approach for these direct tests, since the tests require the authoritative execution and sign-off by the CxA.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy