Who is responsible for Construction Phase Verify SVC Completion/Spot-Check SVC Accuracy?

Explanation:
The on-site commissioning technician (CxT) is responsible for construction-phase tasks like verifying that System Verification Checks (SVCs) are completed and for spot-checking SVC accuracy. The CxA oversees and guides the process, reviews results, and approves them, but the hands-on verification work—doing the checks, recording outcomes, and confirming completion on the job site—is performed by the CxT. The contractor handles installation, but the specific verification duties during construction fall to the commissioning technician role, with the CxA providing supervision and final sign-off. That’s why this option is the best fit.

The on-site commissioning technician (CxT) is responsible for construction-phase tasks like verifying that System Verification Checks (SVCs) are completed and for spot-checking SVC accuracy. The CxA oversees and guides the process, reviews results, and approves them, but the hands-on verification work—doing the checks, recording outcomes, and confirming completion on the job site—is performed by the CxT. The contractor handles installation, but the specific verification duties during construction fall to the commissioning technician role, with the CxA providing supervision and final sign-off. That’s why this option is the best fit.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy