Who is responsible for Construction Phase Monitor TAB Execution?

Explanation:
The on-site task of testing and balancing during construction is done by the Commissioning Technician (CxT). The CxA designs the plan, approves procedures, and reviews results, but the hands-on TAB work—making measurements, adjusting dampers, and documenting data—is performed by the CxT under the CxA’s oversight. This separation ensures objective verification of performance, with the CxT handling the technical execution and the CxA ensuring the results meet the project requirements.

The on-site task of testing and balancing during construction is done by the Commissioning Technician (CxT). The CxA designs the plan, approves procedures, and reviews results, but the hands-on TAB work—making measurements, adjusting dampers, and documenting data—is performed by the CxT under the CxA’s oversight. This separation ensures objective verification of performance, with the CxT handling the technical execution and the CxA ensuring the results meet the project requirements.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy