Who is responsible for Construction Phase Distribute FPTs?

Explanation:
FPT distribution during construction is handled by the on-site Commissioning Team (CxT). They own the day-to-day testing work, including disseminating test procedures, forms, and schedules to the people who will perform the tests (contractors, subs, system operators), coordinating when tests happen, collecting results, and tracking any deviations. The CxA oversees and approves the overall commissioning process and results, but the actual circulation and coordination of Functional Performance Tests happen through the CxT. The Owner mainly receives the final commissioning documentation, while the Contractor may execute the tests under the plan, the distribution and management of those tests is managed by the CxT.

FPT distribution during construction is handled by the on-site Commissioning Team (CxT). They own the day-to-day testing work, including disseminating test procedures, forms, and schedules to the people who will perform the tests (contractors, subs, system operators), coordinating when tests happen, collecting results, and tracking any deviations. The CxA oversees and approves the overall commissioning process and results, but the actual circulation and coordination of Functional Performance Tests happen through the CxT. The Owner mainly receives the final commissioning documentation, while the Contractor may execute the tests under the plan, the distribution and management of those tests is managed by the CxT.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy