Who is responsible for reviewing the DID/OPR during the Pre-Design Phase?

Study for the ACG Certified Commissioning Authority (CxA) Exam. Prepare with flashcards and multiple choice questions, each comes with hints and explanations. Ace your exam!

Multiple Choice

Who is responsible for reviewing the DID/OPR during the Pre-Design Phase?

Explanation:
In the Pre-Design phase, the owner’s goals are captured in the Owner’s Project Requirements and the design approach is outlined in the Design Intent Document. The Commissioning Authority reviews both of these early documents to ensure they are complete, aligned, and testable, and to establish the basis for the commissioning plan. This early validation helps make sure the project design will meet owner expectations and that there are clear criteria for verification later on. While the Project Manager, Architect, and Contractor have their respective roles in delivering the project, the formal responsibility for reviewing the OPR and DID during Pre-Design rests with the Commissioning Authority.

In the Pre-Design phase, the owner’s goals are captured in the Owner’s Project Requirements and the design approach is outlined in the Design Intent Document. The Commissioning Authority reviews both of these early documents to ensure they are complete, aligned, and testable, and to establish the basis for the commissioning plan. This early validation helps make sure the project design will meet owner expectations and that there are clear criteria for verification later on. While the Project Manager, Architect, and Contractor have their respective roles in delivering the project, the formal responsibility for reviewing the OPR and DID during Pre-Design rests with the Commissioning Authority.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy