Who reviews the DID/OPR in the Pre-Design Phase?

Explanation:
In the Pre-Design Phase, the commissioning authority reviews the Owner's Project Requirements and the Design Intent Documents to ensure they clearly reflect what the owner needs and how those needs will be addressed in the design and operation of the building. The OPR outlines performance goals, space needs, project objectives, and criteria for success, while the Design Intent Documents translate those requirements into design-level expectations and proposed solutions. The CxA checks that these documents are complete, measurable, and aligned with the project goals, and uses them to shape the commissioning plan, acceptance criteria, and testing procedures. This early review helps identify gaps and sets a solid basis for verification and validation later in design and construction. While other roles like the Project Manager, Architect, or Contractor play essential parts in their domains, the formal review of the OPR and DID in this phase is the responsibility of the commissioning authority.

In the Pre-Design Phase, the commissioning authority reviews the Owner's Project Requirements and the Design Intent Documents to ensure they clearly reflect what the owner needs and how those needs will be addressed in the design and operation of the building. The OPR outlines performance goals, space needs, project objectives, and criteria for success, while the Design Intent Documents translate those requirements into design-level expectations and proposed solutions. The CxA checks that these documents are complete, measurable, and aligned with the project goals, and uses them to shape the commissioning plan, acceptance criteria, and testing procedures. This early review helps identify gaps and sets a solid basis for verification and validation later in design and construction. While other roles like the Project Manager, Architect, or Contractor play essential parts in their domains, the formal review of the OPR and DID in this phase is the responsibility of the commissioning authority.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy